The Reporter covers Miller, Morgan and Camden County in Central Missouri's Lake of the Ozarks and is published once per week on Wednesdays.
Published August 14, 2019
Camdenton airport expansion continues
CAMDENTON – The continuing airport expansion was the main topic at last week’s
Board of Aldermen meeting.
The city is currently in the process of extending the airport runway from its
current length of 4,000 feet to 5,000. When the project started the city had to
purchase land from 11 land owners in order to complete the expansion.
The expansion will close Forbes Road and relocate the entrance of Hill N’ Dale
mobile home park.
In November 2018, the Board approved an agreement with MoDOT for a grant in the
amount of $172,530 for the City’s Engineering firm, CMT, to Design Runway 15/33
and the Parallel Taxiway Extension Pre-Grading Project.
This included the closing of Forbes Road; Extension of Opportunity Road; and
Extension of Wildlife Fence.
Since then, CMT has done additional work to get the project ready to proceed.
These changes have been reviewed and approved by MoDOT Aviation and an agreement
with MoDOT for an amendment to the original grant of $80,730 for this additional
work with CMT.
Last week the board approved both readings seven separate bills related to the
airport expansion:
• Approved a Supplemental Agreement No. 1 with CMT for design services in the
amount of $89,700.
• Approved a Supplemental Agreement No. 1 with MoDOT for grant assistance in the
amount of $80,730.
The reasons for these changes are due to problems encountered once the process
got underway.
According to the Bill passed by the board, several things came to light.
1. The Camden County Public Water Supply District No. 2 determined that they
could not maintain a water main in a steel sleeve under the runway resulting in
the need to conduct water hydraulic modeling and subsequently design a water
main that would be routed around the end of the runway extension resulting in
new design effort for the water main and revised grading to accommodate the
water main.
2. The level of effort required to coordinate with Camden County on the closure
of Forbes Road and the completion of the new road was dictated by the county and
exceeded the estimated effort in the original agreement.
3. The level of effort required to coordinate with MoDOT and the Hill N’ Dale
Mobile Home Park on the relocation of the park entrance and connection to State
Highway 7 was dictated by MoDOT and the mobile home park and exceeded the
estimated effort in the Original Agreement
4. Additional typical sections were required for the various connections to the
businesses along the new road
5. To aid the contractor in the determination of tree trimming amounts it was
decided to use a drone to aerial survey the trees and then process the data to
create a table showing the amount to be removed from each tree along with the
tree coordinates.
6. Initially Camden County was going to execute a Quit Claim Deed to transfer
any property interests along Forbes Road to the City of Camdenton but was later
determined that condemnation was the best process for each party resulting in
the need for a property survey, appraisal and land acquisition assistance to
complete the condemnation process.
7. The FAA determined that fencing and phasing area critical points should be
submitted separately for on airport and off airport points resulting in the need
to create separate exhibits and make separate submittals.
8. During design it was determined that the best alignment for the new road
would require reconstructing the entrances to the existing businesses resulting
in the need to prepare temporary construction easements, design the new
connections and coordinate the work with each business owner.
9. The City of Camdenton requested the existing property line along the east
edge of the airport be staked and marked with steel posts to help coordinate the
property limits with neighboring land owners.
The board also passed both readings of a bill for more money from MoDOT due to
the changes needed, since the level of funding originally approved is not
sufficient to cover costs associated with this project.
This includes an additional $80,730 from MoDOT with the city providing $8,970.
In addition, based upon the revised project schedule, the original project time
period of September 30, 2019, will be extended to March 31, 2020, to allow for
completion of the work.
A contract with Phillips Hardy, Inc for Runway 15/33, Partial Parallel Taxiway
Extension Pre-Grading, and Extend Opportunity Road at the Camdenton
Memorial-Lake Regional Airport was approved thanks to MoDOT.
City Administrator Jeff Hancock and City Clerk Renee Kingston explained to the
board in their written report.
“For quite some time we have been communicating that we anticipated obtaining a
grant in September from FM and MoDOT to do the grading work for the Runway 15-33
& Parallel Taxiway Extension and the Construction of Opportunity Road. On
Wednesday, July 31 we received notice from MoDOT that FM has approved the grant.
We are now able to proceed with approval of a contract with Phillips Hardy, at a
cost of $4,261,031.44.”
The Board of Aldermen then approved an agreement with Crawford, Murphy and Tilly
Inc for design services for Runway 15/33 and Parallel Taxiway Overlay and
Extension Project at the airport.
Hancock and Kingston again explained why this is needed.
“After we start the grading construction with Phillips Hardy, Inc. the next step
will be to move forward on the actual design of the next phase which will be the
Runway 15/33 and Parallel Taxiway Overlay and Extension Project. To do that we
need to approve a contract with CMT for those design services. The City engaged
another firm to review CMT proposed cost and MoDOT has approved this amount and
contract.”
Project description
1. Perform topographical design survey.
2. Perform geotechnical investigation for overlay and north taxiway extension.
3. Overlay of Runway 15-33.
4. Overlay of parallel taxiway south of apron and all connecting taxiways.
5. Paving of runway and taxiway extension to the south.
6. Grading and paving of taxiway extension north of apron.
7. Removal and installation of PAPI and REIL on Runway 15-33.
8. Installation of Runway 15-33 extension edge lights.
9. Installation of taxiway reflectors along all taxiways.
10. Conduct Aeronautical Surveys in accordance with FAA AC 150/5300-188 for
development of new LPV instrument approaches to Runway 33.
11. Perform Instrument Approach Procedure development coordination.
12. Complete Instrument Approach Procedure Categorical Exclusion.
• Approved an agreement with Crawford, Murphy and Tilly Inc for construction
services
During the grading construction with Phillips Hardy, Inc. MoDOT and FAA requires
the city to have construction services to inspect the work of Phillips Hardy,
Inc. To do this work the City needs to approve a contract with CMT for these
services, which they did.
• Approved the recent MoDOT grant agreement in amount of $387,990.
• Approved another MoDOT grant agreement for $4,383,816.
No specific date has been set when the airport expansion will be finished and
open to air traffic.
All content is Copyright 2019 by Reporter Publishing, L.L.C. Unauthorized reproduction is prohibited without written permission.